P-440 Pier 8 Replacement at Naval Base San Diego

2022 Project Achievement Award
Government: Construction value greater than $50 Million
P-440 Pier 8 Replacement at Naval Base San Diego
Owner: United States Navy / NAVFAC
Project Team: Manson Construction, WSP, MA Engineers, Matrix Environmental, Geo Engineers

Successful demolition was key to a good start. Manson devised an alternative demolition plan with subcontractor Matrix Environmental, minimizing hook time with the floating derrick and increasing production. Additionally, the new bent spacing was increased and shifted, which allowed the new pier pile to miss the old pier pile foundation. This allowed the old piles to be cut at the mudline instead of fully removed, resulting in time and cost savings. Manson successfully achieved completion and delivery of the project in 735 days – 135 days early.